Well, all but the living room floor are stained and laquored now so things are coming together finally. This week the plumber and the electrician come to finish their part of the job. The final thing to be done is installing the kitchen, it is built but we are waiting for the counter top so it can be mounted. I figure I will start moving in stuff some time by the end of the week unless the plumber and/or the electrician can't make it.
Keeping my fingers crossed :-)
-bernt
Well it has been a long time since I posted anything here and things have been rolling forward. The only things that are left now are as follows:
- Staining and lacquering the floors
- Install the lights and sockets
- Installing the toilet and bathroom sink.
- Mounting the kitchen counters
Most of this I hope to have done some time during next week except the kitchen since the counter top doesn't arrive until the beginning of February some time. I figure I can move in without the kitchen done so hopefully I can move in the next couple of weeks. Man this has been a long journey but it is coming to an end finally.
-bernt